A replacement has five stages, and the first one determines how much the rest will involve: assessment of the inherited system, equipment selection, recovery and removal, installation, and commissioning with inspection.
Stage One: What the Assessment Records
The technician is documenting a system that exists rather than designing one that does not. The record covers the outgoing equipment model and refrigerant, static pressure across the air handler, duct condition at accessible joints, line set diameter and insulation state, the condenser pad and clearances around it, breaker and conductor sizing, and the condensate arrangement. A load calculation for the current building runs alongside that, because the house may have changed since the original installation.
Stage Two: Selection Against What Was Found
Equipment is chosen as an AHRI-matched pair sized to the calculated load, and the findings from stage one narrow the field. A duct system already near its pressure limit rules out equipment that expects higher airflow. A tight clearance at the existing pad rules out the larger cabinets. Where the furnace blower cannot deliver what the new coil is rated for, the choice is either different equipment or a wider project that replaces the furnace too.
Stage Three: Recovery and Removal
- Existing refrigerant is recovered into approved cylinders under EPA 608 rules, and the quantity recovered is written into the job file before any component of the circuit is opened.
- The outdoor unit is disconnected electrically and removed, and the pad is assessed for reuse.
- The indoor coil comes out of the plenum, which frequently means cutting and later resealing sheet metal.
- Line set is either removed or, where it is being retained, capped and prepared for flushing and pressure testing.
- Old equipment leaves the site for recycling, and the paperwork for the recovered refrigerant stays with the job.
Stage Four: Installation
The new coil is fitted and the plenum is closed and sealed so that no unconditioned air bypasses it. The outdoor unit is set with manufacturer clearances, the line set is connected and pressure-tested, and the electrical work covers the disconnect, the whip and the low-voltage control run. Condensate is re-piped with the correct trap and slope, and a secondary pan with a float switch is added wherever a leak would reach a finished ceiling. The circuit is then evacuated to a micron target and held to confirm it is dry and tight.
Stage Five: Commissioning and Inspection
Charge is set by the manufacturer method, airflow is verified against the design value, and the technician records temperature split, static pressure, current draws and the final charge weight. Those numbers go on the paperwork that stays with the house. The municipal inspection is coordinated after startup and covers electrical connections, condensate disposal, clearances and equipment listing.
What Sets the Scope
| Factor | What it changes |
|---|---|
| Duct condition and static pressure | Whether sealing or modification is needed before the new equipment can perform |
| Line set compatibility | Reuse after flushing, or full replacement with the access that implies |
| Coil cabinet fit | Sheet metal fabrication where the new coil does not match the existing opening |
| Electrical capacity | Circuit or panel work where the new nameplate exceeds what is installed |
| Access to the equipment | Stairs, crawlspaces and tight mechanical rooms add removal and installation time |
| Condensate route | Pump, secondary pan or new piping where the existing path is inadequate |
Work outside the replacement itself, such as duct replacement, service upgrades ahead of the panel or abatement, is quoted separately once the assessment finds it. Service on the finished system belongs with central AC repair and maintenance, and a house without existing cooling follows central AC installation instead.